Most clients think of a warehouse as just a "box" — and forget that inside there must be proper working conditions: an office for managers, changing rooms and showers for workers, toilets, and a canteen. In Almaty this is not just a comfort issue — it is a requirement of Kazakhstan's labour legislation and sanitary standards for facilities with permanent staff. Let's look at what the interior rooms of a warehouse are built and equipped with.

01

SN RK 3.02-29-2023

standards for administrative and welfare facilities

mandatory requirements for areas, ventilation, and restrooms for industrial facilities

02

1–1.5 m²

cloakroom area standard per 1 worker

minimum per SanPiN RK for industrial and warehousing facilities

03

8–12%

share of interior finishing in the warehouse budget

with a full administrative and welfare block (AWB)

04

GKL + PIR

optimal solution for partitions in Almaty

drywall on seismic-resistant frame + PIR insulation between warehouse and office

Regulatory Requirements for Warehouse Welfare Facilities

What Is Mandatory Under Kazakhstan Law

Per SN RK 3.02-29-2023 ("Public Buildings and Structures"), Kazakhstan's Labour Code, and sanitary standards, with the following number of workers:

Up to 10 people (small warehouse):

  • Toilet: minimum 1 stall separately (M/F)
  • Washbasin: 1 per 15 workers
  • Eating area: not required to be a separate room, but one must exist

10–25 people:

  • Separate M/F toilets
  • Washbasins: 1 per 7–10 people
  • Cloakroom: lockers with locks
  • Eating area (canteen / rest room)

25–100 people:

  • Full AWB (administrative and welfare block): cloakrooms, showers, toilets, rest room, first aid room (for 50+)

When working with chemical/hazardous substances:

  • Showers with hot water mandatory
  • Separate lockers for work and home clothes
  • Decontamination stations

Additional Requirements for Almaty: Seismics

In buildings with load-bearing steel frame structures in the 9-point seismic zone (Almaty), internal partitions must be seismic-resistant. This means:

  • Rigid brick partitions without anchorage to the frame — not permitted
  • Drywall (GKL) partitions on a steel frame with anchorage to load-bearing structures — preferred
  • Fully assembled partition systems (Knauf, Gyproc) — certified for seismic-resistant use

Planning Solutions: Where to Place the AWB

Built-in AWB (mezzanine type)

The most common solution for Almaty warehouses:

  • AWB occupies part of the warehouse volume at a mezzanine level (+4–5 m from the floor)
  • Below the mezzanine — warehouse zone or picking zone
  • Access — directly from the warehouse or from the end of the building

Pros: does not take additional plot area, saves on perimeter walls.

Cons: in case of fire — difficult evacuation; fire calculation required.

Attached AWB (separate block)

  • AWB is a separate building adjoining the end of the warehouse
  • Connected via an airlock vestibule
  • Separate heating and ventilation

Pros: independence from warehouse operations, easier to maintain the temperature regime.

Cons: more expensive (separate foundation and roof), takes up area.

Mobile Modules (container blocks)

  • Ready-made office blocks made of sandwich panels or metal containers
  • Installed inside the warehouse or adjacent to it
  • No project required (up to certain dimensions)

For Almaty: mobile modules are a quick solution, but over the long term they lose out to a capital AWB in thermal performance and seismic resistance.

Partition Materials

Drywall (GKL) on Metal Frame — Optimal for Almaty

For office partitions in a steel-frame warehouse in Almaty$2, the best choice is gypsum board partitions per the Knauf system or equivalents.

System typeApplicationThicknessInstallation cost (₸/m²)
Knauf W111 (single frame)Office partitions125 mm8,000–12,000
Knauf W112 (double frame)Sound insulation, inter-zone150 mm10,000–15,000
Knauf W115 (double sheet)Enhanced strength125 mm9,000–14,000
Moisture-resistant GKL (GKLV)Restrooms, showers125 mm9,000–13,000

Seismic resistance: Knauf systems have passed testing per SN RK 2.03-30-2017; use per instructions ensures seismic resistance up to 9 points with correct anchorage to the building structure.

Brick Partitions

In steel-frame warehouses, brick partitions are not recommended because:

  • Heavy weight → load on the warehouse floor
  • During seismic action — risk of cracks and collapse without special reinforcement
  • Require a separate foundation or a reinforced floor slab

If brick is still used (e.g. for load-bearing purposes) — reinforcement is mandatory every 4 courses and reliable anchorage to the frame.

Sandwich Partitions

  • Steel sandwich partitions (panels with PIR or MW core)
  • Fast installation without wet works
  • Good thermal insulation (between the warm AWB and cold warehouse)
Thicknessλ, W/(m·K)ApplicationPrice (₸/m²)
80 mm MW0.037Warehouse-to-office partitions3,200–4,200
100 mm PIR0.025Warm office with cold warehouse4,000–5,200
120 mm MW (non-combustible)0.037Fire-resistance partitions3,800–5,000

Floor Materials for Office Spaces

Self-levelling Polymer Floors (loft, office)

TypeThicknessCharacteristicsPrice (₸/m²)
Epoxy (self-levelling)2–5 mmGloss finish, easy to clean, chemical-resistant3,500–5,000
Polyurethane2–4 mmResilient, warm, sound-absorbing4,500–6,500
Quartz vinyl (LVT)4–6 mmWood/stone imitation, warm4,000–7,000

Ceramic Tiles (restrooms, showers)

The only normatively recommended material for restrooms and showers.

TypeFormatPrice (₸/m²)
Wall tiles (office)30×602,500–5,000
Floor tiles (R9–R11, anti-slip)30×302,800–5,500
Large-format tiles60×1205,000–12,000
Mosaic for showers2×24,500–9,000

Anti-slip coating is mandatory

In restrooms and showers of industrial facilities, Kazakhstan's standards require floor covering with a slip resistance rating of R9 or higher. Standard office tiles (R7) do not comply — this creates an injury risk and grounds for inspection complaints.

Laminate and Engineered Wood (office areas)

ClassAC ratingSuitable forPrice (₸/m²)
31 (AC3)Residential / light commercialSmall offices2,800–4,500
32 (AC4)CommercialOffices, meeting rooms3,500–6,000
33 (AC5)Heavy commercialCorridors, reception areas4,500–8,500
34 (AC6)IndustrialNot needed in offices — overkill7,000–12,000

For a warehouse in Almaty$2: indoor humidity in the shoulder seasons reaches 60–75%. Class 32+ laminate (with moisture-resistant HDF board treatment) or quartz vinyl flooring is more stable under such conditions than standard laminate.

Ceiling Solutions

Suspended Ceilings (Armstrong type)

Standard solution for office spaces in a warehouse block:

TypeTileApplicationPrice (₸/m², turnkey)
Armstrong (metal frame)600×600 mm, MWOffices, meeting rooms4,500–7,000
Armstrong moisture-resistant600×600 mmRestrooms, kitchens5,000–8,000
Metal strip ceiling84 mm stripCorridors, reception6,000–10,000

Room height: when designing an AWB in a warehouse, the recommended office height is 2.8–3.2 m from the finished floor to the suspended ceiling. Below 2.8 m — uncomfortable for work, above 3.2 m — irrational heating expenditure.

Drywall Ceilings

  • Seamless appearance, curved forms possible
  • Seismic resistance: with correct suspension — up to 9 points (hangers in two directions + rigid elements)
  • Installation cost: 5,000–8,000 ₸/m² (including trimming)

Heating the Office Block: Almaty Specifics

Separation from the Warehouse Zone

The AWB and production zone have different temperature regimes:

  • Office: +18–22°C
  • Regular warehouse: +5–10°C
  • Cold warehouse: 0°C…+4°C
  • Freezer: −18°C…−24°C

An airlock vestibule with double doors is mandatory between them — this retains heat in the office and prevents condensation at zone boundaries.

Heating Systems for the AWB

SystemSuitable forInstallation cost (₸/m²)Consumption over 140-day season
Water radiatorsOffice, cloakroom8,000–12,000Average
Underfloor heating (water)Restrooms, changing rooms12,000–18,000Average
Underfloor heating (electric)Small restrooms4,000–8,000High (electricity is expensive)
Fan coilsOffice with summer cooling15,000–25,000Average

Almaty: summer cooling is just as important as winter heating

In Almaty, summer temperatures reach +35–38°C. An office without air conditioning in July–August is completely non-functional. Cooling the office block is not optional — it is a necessity. Optimal: when designing, plan for a fan coil system with a chiller (works for both heating and cooling) rather than separate split units in every room.

Plumbing and Restroom Engineering

Standards for Number of Plumbing Fixtures

Per SN RK 3.02-29-2023:

Number of workersToiletsWashbasinsUrinals (M)Showers
up to 15111Not mandatory
15–302211
30–503322–3
50–754–5433–4

Materials and Equipment

ElementMinimum classRecommendedPrice (₸/unit)
ToiletWall-hung or floor-standingWall-hung — easier to clean35,000–80,000
WashbasinSurface-mounted or wall-hungBuilt-in with cabinet25,000–60,000
Shower cabinTray + glassOpen shower with curtain40,000–120,000
Mixer tapStandard leverSingle-lever with aerator8,000–25,000
Exhaust fan90–120 m³/h120–150 m³/h4,000–10,000

Pipework: for industrial restrooms in Almaty — plastic-coated metal or polypropylene. Copper pipes — excessive. Drainage — PVC pipe diameter 110 mm with 2% slope.

Approximate Estimate for an AWB for a 1,500–2,000 m² Warehouse

Office block area 200 m² (2 mezzanine floors, 100 m²/floor):

  • Offices: 2 rooms (40 m²)
  • Meeting room: 1 (20 m²)
  • Reception/corridor: 20 m²
  • M/F cloakrooms: 20 m² + 20 m²
  • M/F toilets: 10 m² + 10 m²
  • Utility/server room: 10 m²
ItemCost (million ₸)
Steel mezzanine frame2.5–4.0
Floor slab (profiled sheet + concrete)1.2–2.0
Drywall partitions (150 m²)1.5–2.5
Office finishing (floor, ceiling, walls)2.0–3.5
Restrooms and showers (30 m²)1.8–3.0
Heating + air conditioning2.5–4.0
Plumbing (pipes + fixtures)1.0–1.8
Electrical (lighting, outlets)1.2–2.0
Metal staircase0.8–1.5
Total AWB 200 m²14.5–24.3 million ₸

Average turnkey cost: 70,000–120,000 ₸/m² of AWB area.

We'll include the AWB in the warehouse project — full calculation within 24 hours

StroyHub designs administrative and welfare blocks together with the warehouse — one project, one contractor. Free conceptual estimate accounting for your staffing requirements.

Calculate AWB for my warehouse

FAQ

Is it mandatory to build the AWB immediately, or can it be added later?

If you lay the foundation for an extension — it can be deferred. But connecting utilities (sewage, water) is significantly more expensive after the main construction is complete — you have to break up floors and run routes. Optimally: lay the utilities (pipes to "zero" without fixtures) at the start.

What is the minimum AWB for a 500–700 m² warehouse?

Minimum: 1 M/F toilet with washbasin, a changing area (2–3 lockers), an eating space (small table / kitchen corner). Area: 15–25 m². Can be implemented as a ready-made plumbing module connected to utilities — fast and inexpensive.

Is a cloakroom needed for truck drivers?

By regulation — no, if they are not regular employees. But in practice — it is desirable to provide at least a washbasin and toilet in the loading/unloading zone (separate from the main AWB) for the convenience of drivers and compliance with sanitary requirements.

Ключевой вывод
The administrative and welfare block (AWB) is a mandatory part of a warehouse with permanent staff under Kazakhstan regulations. Critical for Almaty: drywall partitions on a steel frame (seismic resistance), PIR insulation between the office and cold warehouse zone, air conditioning — not a luxury at +38°C in summer. Cost of a full 200 m² AWB — 14–24 million ₸; utilities must be laid concurrently with main construction.