Warehouse real estate in Kazakhstan remains in active growth mode. If you are planning a project, the key question is straightforward: how much will the warehouse cost per m² and what drives the final budget.
from 23,000 ₸
cold warehouse m²
without insulation
from 70,000 ₸
insulated warehouse m²
with sandwich panels
from 110,000 ₸
turnkey m²
with engineering systems
350,000+ ₸
concrete m²
traditional construction
Cost structure
Steel frame
- Cold warehouse: 23,000-35,000 ₸/m²
- Insulated warehouse: 70,000-155,000 ₸/m²
Final frame price depends on span, height, snow/wind loads, and crane requirements.
Enclosure (sandwich panels)
- Wall panels: 8,000-12,000 ₸/m²
- Roof panels: 10,000-15,000 ₸/m²
Typical insulation thickness in Kazakhstan is 100-120 mm, and can be higher for northern regions.
Foundation
- Pile: 12,000-15,000 ₸/m²
- Strip: 14,000-18,000 ₸/m²
- Slab: 16,000-20,000 ₸/m²
Always include geotechnical survey before finalizing foundation type.
Hidden budget items
Engineering systems
Typical range for engineering package: 5,000-15,000 ₸/m² depending on requirements.
Warehouse types and pricing
| Warehouse type | Price per m² | Typical timeline |
|---|---|---|
| Cold warehouse | 23,000-70,000 ₸ | 30-45 days |
| Insulated warehouse | 70,000-155,000 ₸ | 45-60 days |
| Turnkey warehouse | 110,000-290,000 ₸ | 60-90 days |
Prices are indicative for 2026 and may vary by region, configuration, and metal market dynamics.
What has the strongest impact on final price
- Region and logistics
- Soil conditions and groundwater
- Climate zone and insulation thickness
- Building area (economy of scale from ~1,000 m²)
- Extra equipment (docks, ramps, cranes, automation)
Calculate your warehouse budget
Send your parameters and get a preliminary cost estimate with timeline within 24 hours.
Key takeaway
FAQ
How much does a 1,000 m² warehouse cost?
Budget depends on type and engineering scope. For a cold format, cost can start from lower ranges; insulated and turnkey formats scale up significantly.
Is it possible to build in winter?
Yes. Steel-frame assembly is possible year-round, which is one of the key advantages over concrete-heavy workflows.
What is the typical payback horizon?
For many businesses, own warehouse economics often become attractive from a 3-5 year planning horizon, depending on utilization and lease alternatives.