Warehouse Construction Timeline in Almaty: Steel Frame in 2–4 Months vs Concrete in 8–12 Months

StroyHubMarch 20, 20269 min read
Warehouse Construction Timeline in Almaty: Steel Frame in 2–4 Months vs Concrete in 8–12 Months

"How long will this take?" is the second most common question after cost. For any business, time is critical: every month without a warehouse means rental expenses, lost orders, or constrained growth. In Almaty, the situation is further complicated by the mandatory state expert review (seismic zone), which adds 2–4 months to the permitting process. Let's go through the real construction timelines by phase — and calculate how much each "saved" month is actually worth.

01

2–4 months

steel frame warehouse installation

actual construction — with a ready design and building permit in hand

02

6–12 months

monolithic RC warehouse installation

including concrete strength gain at each level and a larger volume of wet work

03

2–4 months

state expert review in Almaty

mandatory procedure for the seismic zone — often the longest phase

04

6–9 months

full cycle steel frame in Almaty

from first conversation to keys — including design, state review, and permits

Why Timelines in Almaty Are Longer Than in Other Cities

Almaty is the only major city in Kazakhstan with mandatory state expert review of design documentation for most industrial facilities. The reason: an 8–9-point seismic zone. This adds 2–4 months to the overall schedule, but it is a non-negotiable procedure.

Additional factors:

  • Workload of permitting authorities (GASKoK Almaty): queues for permit issuance during peak seasons
  • Geological surveys: mandatory, take 3–4 weeks
  • Seismological assignment: 2–3 weeks

Full Construction Schedule for a Warehouse in Almaty$2

Phase 0: Pre-Design Preparation

ActionDuration
Geodetic survey of the site1–2 weeks
Geological surveys3–4 weeks
Seismological assignment2–3 weeks
Obtaining APZ (architectural planning assignment)2–4 weeks
Total Phase 05–8 weeks

Some work can be done in parallel. With good organization — 4–6 weeks.

Phase 1: Design

ActionDuration
Architectural solutions (AR)2–3 weeks
Structural section (KM — metal structures)3–5 weeks
Structural section (KZh — reinforced concrete, foundation)2–3 weeks
Engineering sections (EOM, VK, OV, PB)2–4 weeks
Utility network coordinationparallel, 3–5 weeks
Total design6–10 weeks (parallel)

Phase 2: State Expert Review (Almaty specific)

ActionDuration
Document submission for review1 week
Expert review period6–8 weeks
Addressing comments (if any)2–4 weeks
Receiving positive conclusion1 week
Total Phase 28–14 weeks

State expert review — the longest phase in Almaty

State expert review takes 6–12 weeks. During peak periods (March–June) it takes longer. This time can be partially used to prepare the building site and procure materials. Do not wait for the review to finish before ordering materials — but no construction work can begin before the building permit is issued.

Phase 3: Building Permit

ActionDuration
Filing application with GASKoK Almaty1 week
Permit issuance10–15 working days
Total Phase 32–3 weeks

Phase 4: Construction (steel frame)

WorkDuration for a 1,500–2,000 m² warehouse
Site preparation, axis layout1–2 weeks
Earthworks and foundation sub-base2–3 weeks
Foundation installation (reinforcement + concreting)3–4 weeks
Foundation concrete strength gain28 days (cannot be shortened)
Steel frame installation3–4 weeks
Cladding installation (panels, roofing)3–4 weeks
Gate, window, and trim installation1–2 weeks
Industrial floor construction3–4 weeks (28-day strength gain)
Engineering systems (electrical, heating, ventilation)3–5 weeks (parallel)
Finishing work, system commissioning1–2 weeks
Total construction14–18 weeks (3.5–4.5 months)

Phase 5: Commissioning

ActionDuration
Submitting commissioning application to GASKoK1 week
GASKoK inspection1–2 weeks
Receiving commissioning permit1–2 weeks
Total Phase 53–5 weeks

Overall Schedule: Steel Frame Warehouse in Almaty$2

PhaseDurationParallelism
Pre-design preparation5–8 weeksPartially parallel with design
Design6–10 weeksPartially parallel with surveys
State expert review8–14 weeksParallel with material procurement
Building permit2–3 weeks
Construction14–18 weeks
Commissioning3–5 weeks
TOTAL (sequential)38–58 weeksRealistically 24–36 weeks with parallel work

Realistic turnkey timeline for a 1,500–2,000 m² warehouse in Almaty: 6–9 months.

Monolithic RC Warehouse in Almaty: Why It Takes Longer

Technological Limitations of Concrete

Concrete reaches design strength in 28 days at optimal temperature (+5°C to +25°C). In Almaty's climate, this limitation plays out as follows:

  • Summer (+25–35°C): concrete must be protected from overheating and rapid drying (watering, covering)
  • Winter (−5°C…−20°C): concreting requires heating, special admixtures, covering — time and money
  • Autumn/spring: optimal window, but short

For a monolithic RC building, you must wait for:

  1. Foundation — 28 days
  2. First-tier columns — 28 days
  3. Floor slab (if applicable) — 28 days
  4. Second-tier columns — another 28 days, and so on

Total waiting time just for structural strength gain — several months.

Seismic Requirements for Monolithic RC in Almaty

A monolithic RC frame in a seismic zone of 8–9 points requires:

  • Special seismic-resistant reinforcement (closed ties with hooks, tie spacing half the normal)
  • Seismic shear walls
  • Mandatory designer supervision at every reinforcement stage

This is additional oversight and time.

Comparative Schedule: Steel vs Concrete in Almaty

PhaseSteel FrameMonolithic RC
Design6–10 wks8–14 wks (more complex)
State expert review8–14 wks10–16 wks (more documentation)
Foundation5–6 wks5–6 wks (equivalent)
Load-bearing frame3–4 wks12–18 wks (concrete + strength gain)
Cladding3–4 wks4–8 wks (block walls)
Floor + engineering6–8 wks6–8 wks (equivalent)
Construction total10–18 wks24–40 wks
Full cycle (turnkey)6–9 months8–14 months

Full cycle includes design and state expert review. Steel frame installation alone: 2–4 months; monolithic RC: 6–12 months. Specific timelines depend on area, complexity, and project management.

The Economics of Speed: What Each Month Costs

Scenario 1: Warehouse for Own Use

A company rents 2,000 m² at 4,500 ₸/m²/month (class B in Almaty):

  • Rental expenses: 9,000,000 ₸/month
  • Cost of 6 "extra" months of waiting (RC vs steel): 54,000,000 ₸

Scenario 2: Warehouse for Rental Income

An investor builds a 2,000 m² warehouse to lease at 5,500 ₸/m²/month (class A):

  • Rental income: 11,000,000 ₸/month
  • Cost of 6 "extra" months without rental income: 66,000,000 ₸

Scenario 3: E-Commerce Logistics

An e-com operator loses 3–5% of turnover due to suboptimal logistics when using rented instead of own warehouse. At a turnover of 500 million ₸/year:

  • Monthly losses: 1.25–2.1 million ₸
  • Over 6 additional months: 7.5–12.5 million ₸

Every month faster = real money

The gap between steel frame (6–9 months) and monolithic RC (11–16 months) in Almaty is 5–7 months. When renting an equivalent at 9–11 million ₸/month, that is 45–77 million tenge in rental savings. This exceeds the cost difference between steel and concrete construction for most projects.

How to Speed Up Construction in Almaty

Parallel Workflows

  • Geology + topographic survey + pre-design approvals — in parallel
  • Ordering steel structures at the factory — during state expert review
  • Ordering sandwich panels — after 50% completion of KM design
  • Site preparation — after receiving APZ

Ready-Made Standard Solutions

Standard design solutions (parametric design) speed up documentation development by 30–40%. StroyHub has standard structural schemes for 8–9-point seismic zones.

Choosing the Right Contractor

A contractor with an in-house design department runs design and construction in parallel. The gap between them (first design, then construction tender, then contract) adds 2–3 months.

We will calculate a real construction schedule for your warehouse in Almaty

StroyHub runs design and approvals in parallel — this cuts the total timeline by 2–3 months. Get a detailed schedule for your project within 24 hours.

Get a Construction Schedule

FAQ

Can construction begin before the permit is received?

No. Construction without a permit is an administrative violation. Illegal structures are demolished at the violator's expense. In Almaty (seismic zone), oversight is particularly strict.

What time of year is best to start construction in Almaty?

Optimally, begin installation in April–May so that peak work falls in the warm season (April–October). Concreting in freezing weather (November–March) is possible but requires heating and special admixtures — 15–25% more expensive.

How long does just the steel frame installation take?

For a 1,500–2,000 m² warehouse, installation of the load-bearing frame takes 3–4 weeks with a ready foundation and all structures on site. Cladding — another 3–4 weeks.

Ключевой вывод
A steel frame warehouse in Almaty is built in a 6–9-month full cycle (including design and mandatory state expert review); installation alone — 2–4 months. Monolithic RC — 8–14 months full cycle. A difference of several months at a rental equivalent of 9–11 million ₸/month amounts to tens of millions of tenge in losses. That is why steel frame dominates warehouse construction in Almaty. To shorten the timeline further — choose a contractor with an in-house design department and run parallel processes.