"How long will this take?" is the second most common question after cost. For any business, time is critical: every month without a warehouse means rental expenses, lost orders, or constrained growth. In Almaty, the situation is further complicated by the mandatory state expert review (seismic zone), which adds 2–4 months to the permitting process. Let's go through the real construction timelines by phase — and calculate how much each "saved" month is actually worth.
2–4 months
steel frame warehouse installation
actual construction — with a ready design and building permit in hand
6–12 months
monolithic RC warehouse installation
including concrete strength gain at each level and a larger volume of wet work
2–4 months
state expert review in Almaty
mandatory procedure for the seismic zone — often the longest phase
6–9 months
full cycle steel frame in Almaty
from first conversation to keys — including design, state review, and permits
Why Timelines in Almaty Are Longer Than in Other Cities
Almaty is the only major city in Kazakhstan with mandatory state expert review of design documentation for most industrial facilities. The reason: an 8–9-point seismic zone. This adds 2–4 months to the overall schedule, but it is a non-negotiable procedure.
Additional factors:
- Workload of permitting authorities (GASKoK Almaty): queues for permit issuance during peak seasons
- Geological surveys: mandatory, take 3–4 weeks
- Seismological assignment: 2–3 weeks
Full Construction Schedule for a Warehouse in Almaty$2
Phase 0: Pre-Design Preparation
| Action | Duration |
|---|---|
| Geodetic survey of the site | 1–2 weeks |
| Geological surveys | 3–4 weeks |
| Seismological assignment | 2–3 weeks |
| Obtaining APZ (architectural planning assignment) | 2–4 weeks |
| Total Phase 0 | 5–8 weeks |
Some work can be done in parallel. With good organization — 4–6 weeks.
Phase 1: Design
| Action | Duration |
|---|---|
| Architectural solutions (AR) | 2–3 weeks |
| Structural section (KM — metal structures) | 3–5 weeks |
| Structural section (KZh — reinforced concrete, foundation) | 2–3 weeks |
| Engineering sections (EOM, VK, OV, PB) | 2–4 weeks |
| Utility network coordination | parallel, 3–5 weeks |
| Total design | 6–10 weeks (parallel) |
Phase 2: State Expert Review (Almaty specific)
| Action | Duration |
|---|---|
| Document submission for review | 1 week |
| Expert review period | 6–8 weeks |
| Addressing comments (if any) | 2–4 weeks |
| Receiving positive conclusion | 1 week |
| Total Phase 2 | 8–14 weeks |
State expert review — the longest phase in Almaty
Phase 3: Building Permit
| Action | Duration |
|---|---|
| Filing application with GASKoK Almaty | 1 week |
| Permit issuance | 10–15 working days |
| Total Phase 3 | 2–3 weeks |
Phase 4: Construction (steel frame)
| Work | Duration for a 1,500–2,000 m² warehouse |
|---|---|
| Site preparation, axis layout | 1–2 weeks |
| Earthworks and foundation sub-base | 2–3 weeks |
| Foundation installation (reinforcement + concreting) | 3–4 weeks |
| Foundation concrete strength gain | 28 days (cannot be shortened) |
| Steel frame installation | 3–4 weeks |
| Cladding installation (panels, roofing) | 3–4 weeks |
| Gate, window, and trim installation | 1–2 weeks |
| Industrial floor construction | 3–4 weeks (28-day strength gain) |
| Engineering systems (electrical, heating, ventilation) | 3–5 weeks (parallel) |
| Finishing work, system commissioning | 1–2 weeks |
| Total construction | 14–18 weeks (3.5–4.5 months) |
Phase 5: Commissioning
| Action | Duration |
|---|---|
| Submitting commissioning application to GASKoK | 1 week |
| GASKoK inspection | 1–2 weeks |
| Receiving commissioning permit | 1–2 weeks |
| Total Phase 5 | 3–5 weeks |
Overall Schedule: Steel Frame Warehouse in Almaty$2
| Phase | Duration | Parallelism |
|---|---|---|
| Pre-design preparation | 5–8 weeks | Partially parallel with design |
| Design | 6–10 weeks | Partially parallel with surveys |
| State expert review | 8–14 weeks | Parallel with material procurement |
| Building permit | 2–3 weeks | — |
| Construction | 14–18 weeks | — |
| Commissioning | 3–5 weeks | — |
| TOTAL (sequential) | 38–58 weeks | Realistically 24–36 weeks with parallel work |
Realistic turnkey timeline for a 1,500–2,000 m² warehouse in Almaty: 6–9 months.
Monolithic RC Warehouse in Almaty: Why It Takes Longer
Technological Limitations of Concrete
Concrete reaches design strength in 28 days at optimal temperature (+5°C to +25°C). In Almaty's climate, this limitation plays out as follows:
- Summer (+25–35°C): concrete must be protected from overheating and rapid drying (watering, covering)
- Winter (−5°C…−20°C): concreting requires heating, special admixtures, covering — time and money
- Autumn/spring: optimal window, but short
For a monolithic RC building, you must wait for:
- Foundation — 28 days
- First-tier columns — 28 days
- Floor slab (if applicable) — 28 days
- Second-tier columns — another 28 days, and so on
Total waiting time just for structural strength gain — several months.
Seismic Requirements for Monolithic RC in Almaty
A monolithic RC frame in a seismic zone of 8–9 points requires:
- Special seismic-resistant reinforcement (closed ties with hooks, tie spacing half the normal)
- Seismic shear walls
- Mandatory designer supervision at every reinforcement stage
This is additional oversight and time.
Comparative Schedule: Steel vs Concrete in Almaty
| Phase | Steel Frame | Monolithic RC |
|---|---|---|
| Design | 6–10 wks | 8–14 wks (more complex) |
| State expert review | 8–14 wks | 10–16 wks (more documentation) |
| Foundation | 5–6 wks | 5–6 wks (equivalent) |
| Load-bearing frame | 3–4 wks | 12–18 wks (concrete + strength gain) |
| Cladding | 3–4 wks | 4–8 wks (block walls) |
| Floor + engineering | 6–8 wks | 6–8 wks (equivalent) |
| Construction total | 10–18 wks | 24–40 wks |
| Full cycle (turnkey) | 6–9 months | 8–14 months |
Full cycle includes design and state expert review. Steel frame installation alone: 2–4 months; monolithic RC: 6–12 months. Specific timelines depend on area, complexity, and project management.
The Economics of Speed: What Each Month Costs
Scenario 1: Warehouse for Own Use
A company rents 2,000 m² at 4,500 ₸/m²/month (class B in Almaty):
- Rental expenses: 9,000,000 ₸/month
- Cost of 6 "extra" months of waiting (RC vs steel): 54,000,000 ₸
Scenario 2: Warehouse for Rental Income
An investor builds a 2,000 m² warehouse to lease at 5,500 ₸/m²/month (class A):
- Rental income: 11,000,000 ₸/month
- Cost of 6 "extra" months without rental income: 66,000,000 ₸
Scenario 3: E-Commerce Logistics
An e-com operator loses 3–5% of turnover due to suboptimal logistics when using rented instead of own warehouse. At a turnover of 500 million ₸/year:
- Monthly losses: 1.25–2.1 million ₸
- Over 6 additional months: 7.5–12.5 million ₸
Every month faster = real money
How to Speed Up Construction in Almaty
Parallel Workflows
- Geology + topographic survey + pre-design approvals — in parallel
- Ordering steel structures at the factory — during state expert review
- Ordering sandwich panels — after 50% completion of KM design
- Site preparation — after receiving APZ
Ready-Made Standard Solutions
Standard design solutions (parametric design) speed up documentation development by 30–40%. StroyHub has standard structural schemes for 8–9-point seismic zones.
Choosing the Right Contractor
A contractor with an in-house design department runs design and construction in parallel. The gap between them (first design, then construction tender, then contract) adds 2–3 months.
We will calculate a real construction schedule for your warehouse in Almaty
StroyHub runs design and approvals in parallel — this cuts the total timeline by 2–3 months. Get a detailed schedule for your project within 24 hours.
FAQ
Can construction begin before the permit is received?
No. Construction without a permit is an administrative violation. Illegal structures are demolished at the violator's expense. In Almaty (seismic zone), oversight is particularly strict.
What time of year is best to start construction in Almaty?
Optimally, begin installation in April–May so that peak work falls in the warm season (April–October). Concreting in freezing weather (November–March) is possible but requires heating and special admixtures — 15–25% more expensive.
How long does just the steel frame installation take?
For a 1,500–2,000 m² warehouse, installation of the load-bearing frame takes 3–4 weeks with a ready foundation and all structures on site. Cladding — another 3–4 weeks.