Back to Blog

Hangar Design in Kazakhstan

StroyHubFebruary 20, 20267 min read
Hangar Design in Kazakhstan

Many clients underestimate the design phase — and pay for it during construction. Redoing a foundation or relocating a gate after the pour costs 5–10 times more than corrections on paper. Let's walk through how the hangar design process works in Kazakhstan.

When a Full Design Package Is Required

Under Kazakhstan law (SP RK A.2.2-1-2001), project documentation is mandatory for:

  • Buildings over 500 m²;
  • Structures taller than 15 m;
  • Buildings in seismically active areas (Almaty and the surrounding region — 8–9 magnitude);
  • Structures in specially protected zones.

For small hangars up to 500 m², simplified working documentation may be sufficient in some cases. Check with your local akimat (municipal administration).

Hangar Design Stages

1. Design Brief (Technical Assignment)

The client specifies: intended use, area, height, number of gates, heating requirements, and positioning on the site. A good brief is half the project.

2. Geotechnical Investigation

Borehole drilling and soil analysis. Determines the foundation type. Cost: 150,000 to 500,000 ₸ depending on the site area.

3. Conceptual Design

Overall building layout, dimensions, configuration. Approved by the client before detailed design begins.

4. Working Documentation

Full set of drawings:

  • Architectural solutions (AR);
  • Structural solutions (SR) — foundation, frame, roof;
  • Engineering services (HVAC, plumbing, electrical, communications);
  • Cost estimate documentation.

5. Technical Review (where required)

Buildings above a certain responsibility class undergo state or independent technical review. Duration: 30–45 days.

6. Obtaining a Construction Permit

Issued by the akimat at the location of the site. Duration: 10–30 working days.

Standard vs Custom Project

CriterionStandardCustom
Development time5–10 days3–6 weeks
Costfrom 150,000 ₸from 500,000 ₸
Site specificityMinimalFull
Suitable forStandard structuresComplex and non-standard

A standard project is an adaptation of a proven solution to your site: land dimensions, wind rose, existing utilities. For 80% of projects, this is sufficient.

Factors That Affect Project Cost

  • Building area and complexity
  • Presence of engineering utilities
  • Seismic activity of the area
  • Need to undergo technical review
  • Delivery timeline

We design hangars from scratch or adapt a standard project

Share your project parameters — we will calculate the design cost within 1 day.

Discuss the Project
Ключевой вывод
A project is not an expense — it is a saving. Sound documentation reduces construction costs by 15–30% through optimised structural solutions and eliminating on-site rework.